ONGOING DEVELOPMENT
PHASE 2 OF CLUSTER 1
- TOTAL AREA 2.650 Ha
- AREA INDUSTRY 1.000 Ha
- STATUS FOR SALE (gold)
- CTA to Our Products
INFRASTRUCTURE AND UTILITIES
Cluster 1, Phase 2 Development Status
-
Industrial road access
100 % -
Road light
100 % -
Main drainage
100 % -
Trans Java Toll Access
100 % -
Land clearing 1000 Ha
December 2023 -
Clean Water Installation
2024 -
Waste water treatment
2024 -
Integrated waste management system
2024 -
Electricity
2024 -
Fiber optics
2024 -
Gas supply and piping
2024 -
Flats
2025 -
Seaport
2028
PHASE 1 OF CLUSTER 1
- TOTAL AREA 450 Ha
- AREA INDUSTRY 188 Ha
- STATUS SOLD OUT
INFRASTRUCTURE AND UTILITIES
Cluster 1, Phase 2 Development Status
-
Land grading phase 1 450 Ha
100 % -
Industrial road access
100 % -
Road light
100 % -
Main drainage
100 % -
Trans Java Toll Access
100 % -
Clean Water Installation
100% -
Reservoir
100 % -
Waste water treatment
100% -
Integrated waste management system
100% -
Electricity
100% -
Fiber optics
100% -
Residential (10 towers flats)
100 % -
Gas supply and piping
Desember 2023
CLUSTER 2
- TOTAL AREA 800 Ha
COMING SOON
INFRASTRUCTURE AND UTILITIES
- TOTAL AREA 400 Ha
-
Water Treatment Plan
Phase 1 (450 ha)
Capacity 285 L/s (until 2023)Phase 2 (2.650 ha)
Capacity : 1.072 L/s (ultimate phase) -
Wastewater Treatment Plan
Max Capacity
2 x 9,000 m³/day (until 2023)Entrance Water Quality Limit
(based on Estate Regulation KITB)BOD 400 mg/l
COD 600 mg/l
Nh3 20 mg/l
TSS 400 mg/l
Ph 5,5 - 8
Temp 40°C
Salinity 1 ‰ -
Electricity
Existing Capacity 3 Feeders from GI Weleri with total capacity of 34 MW (installed 2022)
Main Power Station Capacity
2x60 MVA (up to 2024)
Power QualityFrequency 49.5-50.5 Hz;
Voltage 20 kV +5%-10%;
Cos 0.85 Lagging -
Gas
Supply up to 15 MMSCFD (until 2024)
Pressure 350-500 PsiG
GHV 950-1100 BTU/SCF
Water Max 10 lb/MMSCF
Gravity 0,5-0,8
Temp 60°F-120°F
N2 Max 3% mol
CO2 Max 8% mol